PROJECT:   Saraji

  • Medium term planning and design for draglines, truck and shovel
  • Dragsim modelling for the life of mine plan schedule
  • Cut reserves for the 5 year plan for 3 consecutive geological models
  • Short and medium term dragline planning including spoil balancing, strip planning and overseeing production
  • Evaluated contractor tenders for the 30mbcm prestrip contract
  • Quantification of mine closure quantities and rehabilitation scheduling
  • Modified the Xpac model to accept full offset stripping, adding new reserves and adjusting dependancies
  • Haulage calculations and advice on the required fleet size for the P&H4100 and 797 fleet
  • Onsite drill and blast engineering
  • Onsite short term truck and shovel design and planning
  • Onsite management of the coal quality engineer role
  • Ebony Pit Optimisation and pit reconfiguration
  • Generate 5 Year plan dragline and truck shovel quantities site wide
  • Modifications to the site Xact model to interface with Xpac
  • Haulage and landform planning for major pits
  • Optimisation of pit endwall locations for life of asset plan
  • Review and optimisation of the 5 year plan schedule

PROJECT DETIALS:

LOCATION:

Australia

CLIENT:

BMA

COMMODITY:

coal

OPEN CUT / UNDERGROUND:

Open Cut

SERVICES:

3d dig, coal quality, dragline engineering, dragsim model build, drill and blast, equipment selection, haulage planning, long term planning, medium term planning, onsite engineering, rehabilitation and landform, reserving, scheduling, short term planning, tender evaluation, truck shovel engineering, xact model build, xpac model build

DURATION:

2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2014